No | Year | Description |
---|---|---|
P65 | 2006 | Construction of new Unloading Bay, Pipe Gantry and Piping Works |
P66 | 2007 | Drumming Shed Extension |
2013 | Design / Fabrication / Supply and Installation of New Equalisation Tank & Recovery Tank c/w Pump / Piping including C&S Works | |
P67 - P68 | 2013 | Proposed Expansion to The Existing Warehouse for New Beader Plant Main Builder Works and Equipment Fabrication & Erection Packages |